Resources · Job costing

Know what each job is making before it is finished.

Without job costing, a contractor finds out what a job made months after handover, when the year's accounts are closed. By then an overrun is history. Job costing means charging every bill and every hour to the job as it happens, so the margin can be read while there is still time to act on it.

By , founder of Mizarah, who ran a UAE joinery workshop for 13 years · 6 minute read · Updated 2 November 2026 · Practical guidance, not tax advice: confirm anything that matters for your business with your tax agent or the Federal Tax Authority.

The short answer

Job costing for a contractor means charging every supplier bill and every hour worked to the job it was for, setting a cost budget when the job is priced, and comparing the cost so far with that budget and with the work billed. Margin so far is the work billed less the cost so far, both before VAT, and an advance is not billing. Mizarah keeps these figures on every project and lists all your jobs with the ones over budget picked out.

01 · WHAT A JOB COSTSMATERIALS AND LABOUR

Charge every cost to the job it was for.

A job's cost is what you spend to deliver it: the materials and subcontract work you buy for it, and the hours your people put into it. Rent and office salaries are real costs too, but they belong to the business, not to one job.

The rule that makes job costing work is simple: every purchase line and every hour is given its job when it is entered, not at month end from memory.

  • Supplier bills: each line of a bill can go to a different job, so one delivery split across three villas costs each villa its share.
  • Labour: the hours worked on the job at each person's rate, and each entry can say whether it was workshop or site work.
  • Before VAT: VAT you can recover on your return is not a cost of the job.
02 · THE BUDGETSET WHEN YOU PRICE IT

Set a cost budget when you price the job.

The cost budget is what you expect the job to cost: materials, labour and subcontract, before VAT. It comes from the same sums as the quotation, so set it when the quotation is approved, not when the job is already in trouble.

Contract value less cost budget is the margin you priced in. Everything after that is checking whether the job is keeping to it.

A kitchen and wardrobes job, as priced
an example · before VAT
LineAmount
Contract value400,000.00
Cost budget−300,000.00
Expected margin (25%)100,000.00
03 · MARGIN SO FARBILLED LESS SPENT

Read the job while it runs, not after handover.

Three figures tell you how a job is doing: what it has cost so far, how much of the budget that is, and the margin so far, which is the work billed less the cost so far.

Billed means the work certified on your claims, before VAT. The advance is not billing: it is money received for work not yet done, and counting it would make a new job look profitable before any work had started.

Spent so far, halfway through
an example · the same job, before VAT
CostAmount
Materials and subcontract, from supplier bills150,000.00
Labour, from timesheets60,000.00
Spent so far210,000.00

That is 70% of the 300,000 budget, with 90,000 left.

Margin so far
the same job, before VAT
LineAmount
Work billed on claims250,000.00
Less spent so far−210,000.00
Margin so far40,000.00

The 120,000 advance (30%) received at the start is not counted as billed.

04 · BILLED BEHINDEARNED, NOT ONLY BILLED

A job billed late looks worse than it is.

Margin so far depends on how far your claims have caught up with the work. When the work is ahead of the certificates, the job looks thinner than it is. When you have claimed ahead of the work, it looks better than it is.

On a long job, measure the work done by cost: spent so far divided by the cost budget. That share of the contract value is what the job has earned. Compare it with what you have billed. The measure is only as good as the budget: a budget set too low makes a job look further along than it is.

Earned against billed
the same job · work done measured by cost
LineAmount
Done: 210,000 spent of a 300,000 budget70%
Earned: 70% of the 400,000 contract280,000.00
Billed on claims250,000.00
Billed behind: work done, not yet claimed30,000.00
Profit so far: 280,000 earned less 210,000 spent70,000.00

The margin so far was 40,000 only because 30,000 of finished work has not been claimed. Claim it, and the two figures agree.

05 · IN MIZARAHON EVERY PROJECT

Where Mizarah keeps the figures.

In Mizarah each job is a project with a contract value and a cost budget, and the project form shows the expected margin as you type them. Supplier bill lines and timesheet hours are charged to the project as they are entered, and the project shows its budget, spent so far, what is left and the margin so far. Each job also has a costs and margin page with every purchase, delivery, work order and progress bill on one timeline.

The Job costs report lists every job with its materials, labour, spent so far, billed and margin so far, with chips for the jobs over budget, nearly spent (90% of the budget or more) and with no budget yet, and it exports to CSV. Today, the home page, shows your six biggest open jobs with how much of each contract is billed, the retention held and the margin.

Mizarah is cloud only and runs in the browser on a computer or a phone. It costs $49 a month or $399 a year for one company with ten staff logins, after a 14-day free trial with no card for the owner and up to 3 colleagues.

In Mizarah a job's cost comes from its supplier bill lines (draft and void bills are not counted) and its timesheets (one shift for a whole crew, a week in a grid, or a week imported from Excel), the advance is never counted as billed, and the Work in progress schedule shows what each job has earned against what it has billed, with a Recognise button that posts the difference to your books.

QUESTIONS4 ANSWERS

Common questions.

What counts as a job's cost in Mizarah?
Every supplier bill line charged to the job, before VAT, and the hours logged on timesheets for it at each person's rate. Draft and void bills are not counted. A journal you post by hand does not reach a job's cost, so enter a job's purchases as supplier bills.
Does the advance count as billed?
No. An advance is money received before the work is done, so it is not billing. Billed is the work certified on your claims, before VAT. A retention release invoice is not counted again either, because it bills work a claim has already certified.
How do I log labour for a whole crew?
Choose the job, the date, the hours and everyone who worked that shift, and Mizarah writes one line per person at their own rate. A whole week can be filled in a grid, or imported from an Excel or CSV sheet.
Can I cost joinery made in our own workshop?
Yes. A recipe (bill of materials) lists an item's materials with their waste allowance, and its cost check compares what it cost when it was saved with today's prices. A work order compares the material its recipe expects for the quantity with the material actually issued to it.

Read next: Choosing software for a UAE contractor · Retention on UAE fit-out contracts · Pricing